cDeck Forms and Heavy Machinery Arrived

Today our cDeck forms arrived (oops - don't actually have a picture).

The cDeck are basically T-shaped EPS (expanded polystyrene) forms with a thick vertical line that will form (pun intended) the basis of the floor between the basement and the main floor. The forms are about two feet wide and I guess 10 inches high. The vertical "line" of the T is about a foot or so wide. The forms are placed "horizontal bar of the T" down and are shored from below. Then, concrete is poured, forming beams between the foot-wide EPS beams. The concrete then extends another 4" above the forms.

The reasons we went with a cDeck rather than a traditional framed floor are two-fold: primarily we wanted to get a good thermal mass for our passive solar design as well as our masonry stove heating. The 4" concrete floor (and up to 12" where the beams are) will provide a nice thermal mass that will heat up either through the sun or when the masonry stove is on and will provide a nice, even-tempered and slow-changing environment. The mass should also help with keeping the house cool well into the summer. (In the summer months the overhang on the south side will prevent the sun from entering the living room and heating up the mass).
(See our floorplans for more detail (you need to be logged in to our photo gallery for the link to work - ask us for userid and password))

Today also the bulldozer and loader/backhoe arrived for the driveway construction. Our current driveway is somewhat narrow in some places, pretty muddy for the most part, and it has pretty poor water management. So the crew from Clark Construction is going to make it wider, put in about five smaller culverts, dig out a ditch along the north side, grade it and fill it up with 6-12 inches of crushed rock (1-3/4"). That should give us a nice 12-foot driveway.