Tuesday, August 30, 2005

The Windmill is on its way!

Every since I heard from Dennis (our renewable energy contractor from GoSolar in Decorah) that Bergey (our wind mill manufacturer) raised their prices again (and they mostly sell only direct) I've been monitoring the "dirt-cheap" prices on the RealGoods website (they obviously don't update their website too often...). So when we got the green light for our "wind mill pole" building permit last week, I called RealGoods on Friday night an ordered our 84-foot tower and our 1kW XL.1 wind mill. Compared to the current list prices on the Bergey website we saved about $880 - over 25%!

When I ordered the "gear" they quoted me a $270 FedEx shipping fee...although I explicitly mentioned that the website notes that both items will be shipped freigth. So on Monday I called up RealGoods and talked to a nice guy in the technical department...he immediately commented on me getting a good price on the tower set - I saved "$180" and I politely expressed my surprise ;-) But he put me on a conference call with a gal at Bergey and we reserved the gear right away - Dennis had told me earlier in the month that Bergey would discontinue reselling the NRG tower kits and make their own. I had also talked to Steve Wilke from Bergey last week and he mentioned (and confirmed what Dennis had said) that it might be 6-8 weeks until they would be able to ship out the new tower kits - which would take us out to November when it can get quite cold.

Well, today RealGoods confirmed the shipping cost and the total is $390 (which includes a "fee" of $25 for the trucking company to give me one (1) phone call 24 hours ahead of time - they really must have an expensive phone provider.....?). So for $3,850 I got ourselves our supply for all our energy needs (or so we hope). Couldn't have really done it just with Solar Panels....

(quick calculation: six 125W modules for $3,475 plus pole/rack & shipping...750W...6 hours on a sunny day...80%...3.6kW/day -- not even close. We hope to get on average 6-8kWh per day out of the wind mill...but we'll know more in a year).

[Thank you for reading our blog. Please share your comments with us - even if you just want to say you stopped by and read it. Thanks!]

Construction Starts!

Well, on Tuesday August 30, 2005 we finally closed our construction loan at 7:30 AM in the morning at F&M community bank in Chatfield. Mary, our friendly loan officer, helped us to "wade" through the pile of paper work and signatures.

The overall process turned out to be a fairly efficient and painfree one. Of course things took twice as long as I had hoped, but that was still pretty fast, thanks mostly to the good work of Mary who kept things on track and prepared.

Now we have until May 30, 2006 to finish our project!

[Thank you for reading our blog. Please share your comments with us - even if you just want to say you stopped by and read it. Thanks!]

Tuesday, June 21, 2005

Propylene Glycol in your Ice Cream

One of the things we learned at the MREA fair is that it makes good sense to go with a Solar Hot Water System for pre-heating our household water as well as to use it for our radiant floor heat. Obviously if we are going to use it in the winter, we need to protect it from freezing, which is why we need to use some antifreeze. The antifreeze most commonly used in these applications (usually environmentally conscious people) is Propylene Glycol. Interesting enough I learned that Propylene Glycol is used in ice cream (to prevent it from freezing rock hard). Here is a good article from Tom's of Maine about their use of Glycol and alternatives.

[Thank you for reading my blog. Please share your comments with us - even if you want to say that you stopped by and read it. Thanks!]

So many news...

Well we just went to the MREA fair 2005 and returned with lots of information in our brains.. The next posts will deal with some of the topics we dealt with. If you live within driving distance from Stevens Point, Wisconsin I highly recommend attending the fair. We had a blast!

[Thank you for reading my blog. Please share your comments with us - even if you want to say that you stopped by and read it. Thanks!]

Tuesday, May 24, 2005

Embodied Energy

This is really interesting:
One insulating unit (insulation required to provide R-20 for a square foot at normal density) of cellulose has 600 BTU of embodied energy. EPS (expanded polystyrene - CFC-free insulation material used for our walls and probably also the roof) has 18,000 BTUs in the comparable amount of insulation...
http://www.buildinggreen.com/auth/article.cfm?fileName=040101a.xml

Our house's surface area is roughly 3,750 sq.ft. for the walls (R-22 with ICFs) and 2,750 for the roof (R-40 with SIPs). This means our embodied energy, in just the walls and roof is 165.6 Million BTU or 48,535 kWh, i.e., as much electrical energy as we plan to consume in over 26 years. And then there is the cement...and the floor slab with EPS...

But hey - if we burn 2 cords a year, it's only as much as 8 years of using our masonry stove ;-)

(in comparison, if we'd use cellulose in the roof, it's only 1/2 year of electrical energy (instead of 16 years))

Electricity ..... 3,412 Btu/kilowatthour
Natural Gas ..... 1,031 Btu/cubic foot
LPG (Propane) ..... 91,330 Btu/gallon
Wood ..... 20 million Btu/cord

[Thank you for reading my blog. Please share your comments with us - even if you want to say you stopped by and read it. Thanks!]

Friday, May 20, 2005

Window, window, in the wall...

...which is the most efficient of them all?

Well, it's time to do some window research again...this time I'll try to take notes so that I don't forget everything again...My first stop for windows research has always been energyefficientwindows.org. Reading through their pages and using their window selector, it seems that we want the following windows:
  • on the south side - window 30:
    double-glazed, high-solar-gain, low-e, argon gas, insulated vinyl
    (U value of 0.29, SHGC of 0.56 and VT of 0.58).
  • on the east/west sides - window 33:
    triple-glazed, moderate-solar-gain, low-e, argon gas, insulated vinyl
    (U value of 0.18, SHGC of 0.40 and VT of 0.50)
The U-value indicates how well the window insulates (i.e., keeping the heat in); the Solar Heat Gain Coefficient (SHGC) indicates what percentage of the sun's energy is allowed to get through (and heat our cement slab and other thermal mass); the Visual Transmittance (VT) indicates how much "dayligh" makes it through the window (the lower, the darker).

As I see now, "Insulated Vinyl" has become as energy-efficient as our previously favored Fiberglass. The challenge will be to find a company that makes windows with these characteristics, because it seems that this model windows are just hypothetical windows and don't represent any physically available windows...


[Thank you for reading my blog. Please share your comments with us - even if you just want to say you stopped by and read it. Thanks!]

Thursday, May 19, 2005

Official Kick-Off

Well, tonight I finally followed through on promises made in the past months...I finalized the plans and the 3D model and sent a note off to Jim from Holabird & Root. We had met with Jim in December 2003 to review our plans (log house with garage in basement back then). And wouldn't you know it? Jim worked with Andy Bunge on two projects last year and this year (Andy's brother's house and the Commonweal Theatre Addition. It's a small world...

So, the countdown can begin...here's what's on my list:
  • Get plans reviewed by architect
  • Get blue prints
  • Secure ICF forms contractor
  • “Organize” driveway gravel build-up
  • Develop budget with Andy
  • Apply for Mortgage
  • Contact Masonry Stove builder in Wisconsin
  • Create preliminary plumbing plan
  • Create preliminary electrical plan
It'll be a busy, fun summer!

[Thank you for reading my blog. Please share your comments with us - even if you just want to say you stopped by and read it. Thanks!]

Thursday, May 12, 2005

Shading through the south-side overhang

Yesterday when I shared the 3D Model slide show with my colleague Jim, he inquired whether the soffit overhang on the south side will provide enough shading in the summer.

Well it had been about 1.5 years since I last researched "sun altitude" and "sun azimuth". In the meantime the geometry of the roof and south wall had changed quite a bit, so it was time to confirm the sizing of the overhang. I found this site from the U.S. Naval observatory to get sun (or moon) altitude and azimuth tables for a given date at a given location.

Seasonal Sun Penetration - click to see full sizeIn the picture on the right you can see the different penetration levels at 12 PM noon on June 21, March & September 21 and December 21. As you can see, the overhang completely shades the midday sun in the summer (most left beam) whereas in the winter, even at high noon, the sun will penetrate as far as the back wall of the living room. (Click on the picture to open a full-size version in a separate window.)

The other study/simulation that I did, is to simulate the actual penetration during the middle of the summer. Two values determine the suns position: the sun altitude (i.e., the angle of the sun up from the horizon; 0° being on the horizon and 90° being directly above) and the sun azimuth (i.e., the angle along the horizon, with 90° being east and 180° being south). So the actual penetration through the south windows is not only a factor of the sun's altitude and the overhang geometry and window height, but also of the sun's azimuth and the windows' widths. The image below shows the penetration at 9:45 AM (yellow) and 14:35 PM (orange). As you can see only a fraction of the possible direct sunlight can enter the room during these times,Seasonal Sun Penetration - click to see full sizesince the sun is pretty much still in the ESE (112.5°) or WSW (202.5°). The suprising thing for me was that the overhang pretty much prevents even that early sun to penetrate the room - the deepest penetration is about 3 feet (at an azimuth of 109° with an even lower percentage of what makes it in). and the penetration rapidly declines to zero by around 11:10 AM and does not penetrate at all until 13:10.

As some of you might recall, on the east side of the dining room, we do have the same large windows as on the south side, but with no overhang (at least only in the gables), so the sun will penetrate the living room from that side for the most part of the morning. This is actually by design, because in the spring time, it tends to stay pretty cold (yesterday the high temperature was 42°F), especially in March or April. At our place the sun rises pretty much in the east, but due to some trees we probably won't see much of it until it is about 10° high, at around 7 AM at 10° south of east. For the summer, when the sun reaches 10° altitude at 5:40 AM in the ENE (67.5°) we definitely will have to employ shades on these windows. Fortunately, and also by design, this is not so much of a problem on the west side, where the windows are much smaller, due to the sitting area. But shades would probably also help here as well.

Sun Penetration Graph - click to see full sizeThe last simulation I ran with the data is to plot the penetration depth for each of the four dates. The graph on the right shows the penetration level at the various times of the day for the four dates during the year. The nice thing that you can see is that the penetration during the winter time can reach the backwall unhinderedly when the sun's azimuth is between ESE and WSW.

In summary, the theory looks good for the sizing of our overhang on the south side. The 80" (6' 8" or 203 cm) windows now allow unhindered penetration into the room during the winter months which should help with the heating on sunny days. The 475 sq. ft., four inch thick cement slab definitely will have enough capacity to store any heat coming through the windows, and with 168 sq. ft. of window space for 1,500 sq. ft. of main and 2nd floor living space (i.e., 11%), we might be a little bit over the recommended percentage for south-facing glazing, but we'd rather shade windows in the summer time then having to freeze. And our large thermal mass (including the masonry stove) should help mitigate overheating. We can also always open the door to the basement - to add another 1,100 sq.ft. of living space...(or the garage to add 485 sq. ft.).

Wednesday, May 11, 2005

Update on Project Licht 'n Stein

Well, it has been almost 15 months since the last blog entry.

But finally, there's a little bit more life in our project -- last weekend during the Kid's Philosophy slam in Lanesboro I had a chance to chat with our General Contractor and it seems that since he is still very interested in shepherding our project.

So hopefully, given the already advanced year, we might get at least an enclosed structure (i.e., concrete walls, windows, & roof) and masonry stove done before winter, which would make us self-sufficient (i.e., heating, water & electricity) to finish the interior during the winter...

The next steps for me are:
  • share the revised floor plans & 3D Model (see link below) with the architect and get some load calculations done and probably some blueprints drafted
  • get estimates for some driveway buildup
  • contact concrete contractors (such as Wellik out of Stewartville) to check their availability.
Below are some links to some updated information.

What's New
Slide Show of the 3D model (and floor plans)
Updated (but not completed) description of components
especially: shelter & water

Sunday, February 08, 2004

Dinner on the Bluff

Last night we went to one of the "Dinner on the Bluff" series organized and hosted by the Eagle Bluff Environmental Learning center. Last night's event's topic was "local flavors" and we enjoyed a fabulous menu of locally grown and raised flavors masterfully prepared by chef Laura Thompson.
We spent a fabulous time with Katie & Harlin as well as Jim and Fred. For a long time I've wanted to talk to Fred, since he is one that has a nice wind turbine right behind his house (the big white timberframe south of town). I am a little concerned that he mentioned that his 20 kW Jacobs Wind Turbine does not perform as well as he expected, but he explained that it could be a function of where they placed the turbine.
I also finally had a chance to introduce myself to Joe Degen, Executive Director of Eagle Bluff. I had found out that they have installed an anemometer (wind meter) and was interested in getting a hold of the data. It turns out that Eagle Bluff does not have an anemometer installed at their site, but on the Fountain tower and one in Pilot Mound.
Joe also introduced us to his wife, Mary Bell, who has a strong interest in Wind Energy and writes for the Fillmore County Journal. Especially an article about Garwin McNeilus that she wrote a while back, is very encouraging, as it mentions that Garwin has plans to build a 10kW turbine for $10,000.
Once again we find ourselves renewed in our excitement about moving to this community of interesting, smart, open-minded and environmentally concerned people. We hardly can wait to move!

A visit with IPS

This Friday we went up to the cities to finally visit with the renewable energy firm that I had found on the web, Innovative Power Solutions. Their website (especially their "Build your own system" link from the homepage) has been quite helpful in designing our electrical system.

We met for over one-and-a-half hours with Roger, Mario and Lobos. Mario had some very good feedback on various aspects of our design and we feel comfortable moving ahead working with them on our system.

News from my Dad

Last weekend my mom called to let me know that my dad is in the hospital (again). As some of you know, my dad had an "aortic aneurysm fixed with goretex" in the fall of 2000, but as the surgery took much longer than expected (6 hours), it was very hard on his body. He was on the ICU for almost 6 months and for the first 5 months in a coma and the doctors almost giving him up after he developed antibiotic resistancies. But then, around January/February of 2001 he suddenly bounced right back, went to rehab and was just the same. Amazing!

So, needless to say to hear the news that he's back in the hospital brings back some memories. But my mom and dad are vey optimistic. It turns out that he was not feeling well last Saturday and decided that there was no way that he would go to bed that night with such a strange feeling regarding his heart. Also his bloodpressure was just way to high, so around 10 PM they called the hospital and after describing the symptoms, they sent an ambulance. After some tests and a relocation to a heart-specialty clinic, it turns out that he will need a triple bypass.

Righ now the surgery is scheduled for Wednesday, the 18th. We'll keep our fingers crossed!

Sunday, February 01, 2004

Detailed Design Reviews started

Last Wednesday we finally started our 'detailed design review series". The first topic was "log homes" and I shared some of the things that we learned. The invitation to the design reviews goes out to 50 of our colleagues at Mayo and we are grateful for their time and feedback. Their interest in our project is a great motivator for us! Next Wednesday, the 4th of February, we will start talking about the electrical system.

Tuesday, December 23, 2003

Design Review Coming Up / Floorplans Posted

Tomorrow, on Christmas Eve, from 11:30 AM to 1:30 PM we will hold our first formal semi-public design review in the Medical Sciences Building, Mann Hall.
~~~
I posted our floorplans - take a peek!

Sunday, December 21, 2003

Good Advice

Bob & Marissa, friends of Todd & Eva, gave us some good advice that we will try to incorporate into our plans. Between the two of them they built 5 or 6 owner-built, sustainable houses employing renewable energies. Right now they have a house near Winona and are employing rainwater collection (2,500 gal cistern) a Masonry Stove and photovoltaic panels (six 120 W Kyocera). And their house, which only has one floor, has a footprint of 24 by 37 feet, very close to our 24 by 36 feet (and I wouldn't mind another foot in the bathrooms...or the stairs...

Here their advice to us: Insulate your foundation footings and basement walls and basement slab on the outside. "2 inch of foamboard can do wonders", Bob said. And: Place the closets on the north wall.

Architect on Board

Last Thursday we visited with a super-nice architect. Jim G. from Holabird & Root out of Rochester was very interested in our mini-project. Based on our needs we agreed that his firm could help us best by providing us with advice when we need it on an hourly basis. Thankfully he confirmed that with pre-fab panels we should have no problem covering the basement with a cement slab (that we need for passive solar heat storage). His first service to us will be a walking of the site on January 2nd to help us place the house, the garage and the driveway. This should be fun!

Sunday, November 30, 2003

A walk in Lichtnstein

This afternoon, on a gorgeous sunny day (52°F!) we made out to the property for a nice brunch & walk. Since the previous owners were so thoughtful to take their picnic table with them, we hauled our picnic table in and had a quick Subway lunch. Then we set out towards the west half of our south border to post some more signs. That piece of the property is probably the one that we will see the least of, since it is not easily accessible. However now with all the leaves gone it is truly gorgeous! There are a lot of hidden bluffs and rocks and trees (birch trees). At the bottom of the steep hill there is a wide ditch that probably hasn't seen water in a long time - if the size of the trees that are groing in the ditch are any indication.

After our walk, as we were leaving the property, we met Tom our westerly neighbor who was gonna check up on the property. Tom's the son-in-law of the farmer who originally owned the land.

Well, that's the news for this weekend.

A spontaneous trip

Well on Friday afternoon we spontaneously decided to do an 800 mile trip down to Missouri and take a look at Gastineau's show rooms in Missouri. Mapquest told me that it would take 8 hours and 530 miles, but that was on thei Highway going way west through Kansas City. After I stumbled across US 63 near the site where they have their show houses, we decided to go south on Country Roads - because we happen to live right on 63 ;-) Well that was at 1:20 PM and at 2:05 PM we were in the truck, heading south to Columbia, MO -- 370 miles according to Mapquest. I even found a Thai restaurant in downtown Columbia, so off we were. Jennifer took the first turn driving, since I still had to do some work for work and as we got halfway to Oskaloosa at 5:15 PM, I had accomplished what I needed to accomplish and took the 2nd half driving. If you ever have to go straight south from the Twin Cities, take 63, it's a nice drive!

We were actually lucky driving down there this weekend as we met not only the person who is familiar with our "case", Janet Groat, but also had a chance to meet and talk to the President of Gastineau, Lynn Gastineau. All-in-all it was a very informative trip that answered some questions but also created some new ones. At least we are still convinced that we want a log home.

Plans are worthless, planning is essential

This morning we finally got around to entering all the things we'll need to do into a project plan. It's quite an undertaking, but it looks like a lot of fun, too. We'll probably be looking at another Log Home up in the cities next weekend and also this week I want to get in touch with the people at IPS. According to the plan I need to create a project overview, so that's probably what I'll be working on tonight. And wrapping up some of the loose ends from our visit with Gastineau, too.

Thursday, November 27, 2003

Maps, Drawings & Pictures

For all those of you for whom a picture says more than a thousand words I have started posting a few pictures, maps & drawings about and around Licht 'n Stein. Enjoy the slide show!
http://lichtnstein.org/gallery/lns

Happy Thanksgiving - if all goes well, we'll have a house warming party a year and 2 days from now, the Saturday after Thanksgiving...

chris